    CONSTRUCTION UPDATES

    Offices at The Block Are Anticipated to be Ready for Move-In Q1, 2024

WATCH THE BLOCK GROW SKYWARD

The Block is under construction and steadily making progress towards its anticipated completion in Q1, 2024. Keep an eye on this page for regular updates as the building progresses!

Construction Updates
February 2023
Bernard Block Construction Updates 12
New Year, New Level

Construction is progressing smoothly with concrete pouring complete to Level 11. Masonry, fire protection, mechanical, and electrical work is underway from Levels 1-5.

Bernard Block Construction Updates 12
December 2022
Bernard Block Construction Updates 11
Level 9 Poured

Precast cladding is now complete on the South and East elevations. The Level 10 typical floor on Bertram and Level 9 on The Block have been poured.

Bernard Block Construction Updates 11
October 2022
Bernard Block Construction Updates 9
Slab Pour

With the final pour of the Level 6 transfer slab, the parking structure is complete. We'll now watch as the tower steadily rises to its full 17-storey height.

Bernard Block Construction Updates 9
September 2022
Bernard Block Construction Updates 8
Level Five Vertical Complete

The team completed the Level 5 vertical as well as all slab decks forming for Level 6.

Bernard Block Construction Updates 8
August 2022
Bernard Block Construction Updates 6
Formwork Begins on West Quadrant

This month the team began formwork on the west tower quadrant and completed the east vertical concrete for Level 5.

Bernard Block Construction Updates 6
May 2022
Bernard Block Construction Updates 5
Vertical Progress

The Block continues its upward momentum with the slab for Level 2 having been poured. The pour for Level 3 is anticipated for early June.

Bernard Block Construction Updates 5
February 2022
Bernard Block Construction Updates 4
Slab Work Begins

The first slab-on-grade is poured, marking the first step in The Block’s vertical progress.

Bernard Block Construction Updates 4
March 2021
Bernard Block Construction Updates 3
Foundations are set

262 pilings are driven into the ground with innovative, vibration-reducing technology, setting the stage for the first concrete pour.

Bernard Block Construction Updates 3
January 2021
Bernard Block Construction Updates 2
Bernard Block breaks ground

Construction officially kicks off for The Block. Work begins to excavate the site for pilings and below grade operations.

Bernard Block Construction Updates 2
January 2021
Bernard Block Construction Updates
Demolition Begins

Fencing is installed and crews begin to demolish the existing structure. Demolition is complete after 86 days.

Bernard Block Construction Updates
June 2020
Bernard Block Office 7
Development Permit Approval

Downtown Kelowna’s first Class A office tower is approved by Kelowna city council. Next door to master-planned residential communities Bertram and Brooklyn, The Block is set to bring a new energy and commercial hub to downtown like never before.

Bernard Block Office 7

Bernard Block 25

CONTACT US

Please reach out for more information on leasing opportunities at The Block:

STEPHEN WEBBER

Associate Vice President

250.861.8104

Stephen.Webber@Colliers.com

JASON TEAHEN

Senior Vice President

Personal Real Estate Corporation

604.661.0847

Jason.Teahen@Colliers.com

ROB CHASMAR

Senior Vice President

Personal Real Estate Corporation

604.661.0822

Rob.Chasmar@Colliers.com